Winfield Unified School District #465

WHS Practice Track Update

The WHS Practice Track is currently under-construction.
 
To date the following steps have already been completed:
- Clay and dirt sub base of the track was removed.
- Fabric covering was applied to all of the track oval.
- Rock fill mixture obtained from local sources was spread out across the track oval.
 
Application of asphalt layers will be the next step in the track renovation process.  During this time it is vital everyone stay off and stay clear of the track area.  This process will take a minimum of 28 days to finalize and cure. Thank you for your support and attention to this matter. 

Published Print